What's the status of various area projects?

 Fredericksburg officials have been working since 2007 to upgrade the city's court facilities. They haven't yet settled on a location or a plan.
FILE/THE FREE LANCE-STAR
View More Images from this story
Visit the Photo Place
Date published: 3/5/2011

continued

--Cathy Jett

State Route 3 extension

The story so far: Workers are widening a four-lane portion of State Route 3 in Spotsylvania from Chewning Lane and Rutherford Drive to Gordon Road. It's the last section of the road with four lanes between Interstate 95 and the Harrison Crossing shopping center.

Outlook: Construction is proceeding on target to widen Route 3 to six lanes near Gordon Road by the summer of 2012.

When the project is completed, six median crossovers on Route 3 where vehicles made left turns and U-turns will be closed. Traffic will instead use turn lanes and traffic signals at four intersections: Chewning Lane and Rutherford Drive, Chancellor Village and Single Oak Road, Old Plank Road and Five-Mile Fork Extended, and Gordon Road.

--Cathy Jett

Town Center at Aquia

The story so far: Ramco-Gershenson Properties Trust is in the process of transforming Aquia Town Center in Stafford from a 200,000-square-foot grocery-anchored shopping center into a 725,000-square-foot mixed-use development featuring offices, retail and restaurants, entertainment and fitness, and high-end apartments.

Outlook: The former Big Lots building has been torn down, and additional site work has been done. "The deal is still progressing," said Thomas W. Litzler, executive vice president for development and new business initiatives.

--Cathy Jett

VRE IN SPOTSYLVANIA

The story so far: After more than a decade of voting down the Virginia Railway Express, the Spotsylvania Board of Supervisors last year finally approved joining the commuter rail network.

Outlook: First a station has to be built in the county. Spotsylvania's supervisors have selected a site in the Crossroads Business Park. VRE is now designing a third track between the proposed station and a point just south of the Fredericksburg train station, which track owner CSX requires before service begins. Then the VRE must secure funding for construction and get the track built. VRE officials think it will be ready in 2013, though Spotsylvania officials are hoping for next year.

--Bill Freehling


Previous Page  1  2  3  4  5  6  7  8  9  

AMELIA SQUARE

IT'S BEEN A TOUGH SELL

HAVEN APARTMENT PROJECTS

SECOND COMMUNITY IS IN THE WORKS

RIPKEN FIELDS

FIRST PHASE ALMOST DONE

CARMEL CHURCH STATION

IT'S STILL IN THE STUDY STAGE

COURTHOUSE

RESPONSE CUTOFF WAS MARCH 1

MUSEUM OF THE CONFEDERACY

LOCAL SITE STILL IN CONTENTION

COBBLESTONE SQUARE

PROJECT IS FINALLY MOVING

COWAN BOULEVARD PROJECT

COWAN CENTER IS FILLING UP

CROW'S NEST

STILL CLOSED TO THE PUBLIC

FALL HILL AVE.

MAJOR WORK TO BE IN 2013

FALMOUTH INTERCHANGE

CONSTRUCTION TO START IN 2014

GERMANNA'S STAFFORD CAMPUS

GOAL FOR FULL STAFFORD CAMPUS IS 2018

KALAHARI RESORT

STILL SEARCHING FOR FUNDING

KING GEORGE GATEWAY

CONSTRUCTION IS UNDER WAY

VRE STATION IN SPOTSY

LOOKING AT 2013 OPENING

K.G. GREENHOUSE PROJECT

FEW DETAILS ON ORGANIC PROJECT

FALLS RUN AND STAFFORD LAKES SHOPPING CENTER

PAD SITES GRADED AT FALLS RUN

McKESSON PROJECT IN CAROLINE

TARGET DATE IS EARLY 2012

NATIONAL MUSEUM OF THE MARINE CORPS

MAIN MUSEUM, GALLERIES DONE

NEW POST SOCCER FIELDS

LAND TRANSFER THIS YEAR?

SPOTSYLVANIA TOWNE CENTRE AND THE VILLAGE AT TOWNE CENTRE

VILLAGE IS FILLING UP

RIVERFRONT PARK

OPENED LAST YEAR STATE ROUTE 3 EXTENSION

CONSTRUCTION IS ON TARGET

QUANTICO EXPANSION

NEW PERSONNEL TO BEGIN MOVING IN

SPOTSYLVANIA COURTHOUSE VILLAGE

PHASE TWO REZONING COMING THIS YEAR

CROSSINGS AT FALLS RUN

SENIOR-LIVING CENTER COMING SOON

TOWN CENTER AT AQUIA

SITE WORK BEING DONE

EAGLE VILLAGE/UMW

FIRST PHASE FINISHED

NEW YMCAs

NO CONSTRUCTION DATE YET

I-95 PROJECTS

HOV/HOT LANES WILL EXTEND TO STAFFORD