In a somewhat anti-climactic finale, the Spotsylvania Board of Supervisors on Thursday night approved special-use permits for two other tracts of the massive solar facility in the western part of the county.

For more than a year, the proposal to build one of the country’s largest industrial solar facilities has dominated county meetings, which have consistently been packed with supporters and opponents.

With the supervisors approving the largest section of the 500-megawatt solar facility on Tuesday, the crowd was much lighter Thursday night.

Following a brief overview of the two other sections of the project and changes to several special-use permit conditions, the supervisors approved the proposals.

Supervisor David Ross was the lone no vote on all three permits. Board Chairman Paul Trampe voted no on the two larger sections.

Utah-based Sustainable Power Group applied for the special-use permits in late 2017. The company, also known as sPower, plans to build the massive, $615 million facility on more than 6,300-acres in the Wilderness area, where 1.8 million solar panels will be installed on the three tracts.

The solar farm, the largest such proposal in the nation, would send energy into the current grid. The company already has agreements to sell the electricity to Apple, Microsoft and the University of Richmond.

Residents around the proposed site said the project is too big, includes too many unknown health and environmental risks and is a financial gamble for the county and residents, among other issues.

The company countered with experts who deemed the project safe. SPower projects the county will receive $21.1 million total in new tax revenue from facility over the life of the project and $25 million in additional funds from the company.

The county’s Planning Commission recommended that supervisors deny the two larger and approve the smallest one. The county’s Planning Department recommended the supervisors approve all three permits, but with the many strict conditions.

Opponents have criticized supervisors who approved the project, suggesting they caved in to sPower.

Charlie Payne, a local attorney representing the company, said the more than 170 conditions the county attached to the permits probably makes the project most heavily regulated solar facility in the country. He said the conditions protect Fawn Lake residents.

“They should thank the board,” he wrote in a text message.

The company expects to have the facility operating within two years.

Get our daily Headlines Newsletter

* I understand and agree that registration on or use of this site constitutes agreement to its user agreement and privacy policy.

Scott Shenk: 540/374-5436

sshenk@freelancestar.com

Recommended for you

Load comments